Attachment 2 - Alabama Bulletin No. AL300-7-2
Definition Document
Conservation Program Contracts (CPC's)
Recovery of Costs for Cancellation and Termination,
Alabama - April 2007
Policy for contract cancellation or termination is found in Conservation Program
Contracting (CPC), Part 512.57-58 of the 440-V-Conservation Programs Manual,
Amendment 30, August 2005. A CPC may be either cancelled by both parties, or
terminated for cause by NRCS. In either event, the obligations contained in the
CPC are ended through action that annuls the responsibilities of both parties to
the contract. The participant is informed in writing of forfeiture of all future
payments under the contract and repayment requirements, as applicable.
Cancellation: Equitable remedy that allows both parties to the contract to end
the contractual relationship. Contract participants must request cancellation in
writing, provide reasons for the cancellation request, and if applicable,
provide information on availability of any transferees. Reasons for cancellation
may include but are not limited to documented hardships such as major illness,
bankruptcy, death, destruction of farm property through fire or theft; natural
disaster preventing completion of contract provisions; and in the public
interest and beyond the participant’s control.
Termination: Result of material breach of the CPC terms and conditions
(termination for cause). Terminations for cause will usually result in an
assessment of liquidated damages for a recovery of costs associated with the
administration of the breached contract. Termination can occur at any time if it
is determined that the participant or land becomes ineligible; participant
transfers ownership or loses control of land under contract; participant has
violated the terms of the contract and has failed to correct and comply within a
reasonable time; participant fails to install, operate or maintain one or more
practices or activities required; participant’s actions pose a threat to the
health and safety of NRCS employees; and use of scheme or device.
Recovery Costs: Applies to both technical assistance and financial assistance.
This includes an estimated value of technical assistance (liquidated damages)
and a refund of financial assistance (cost share obligations). Refer to the CPC
Appendix to determine if cost recovery applies to the contract in question.
Liquidated Damages: A participant may be assessed liquidated damages up to 20
percent of the total cost-share funds obligated to the contract when it was
developed. In Alabama, contracts written prior to 2003 will not be assessed
liquidated damages. With justification, the State Conservationist (STC) has the
option of waiving all or part of the liquidated damages. WHIP contracts will not
be assessed liquidated damages, because there are no regulatory or CPC Appendix
provisions that allow such an assessment. Contracts cancelled in the same fiscal
year they are developed will not be assessed liquidated damages if the contract
is cancelled before August 1.
EQIP and CSP: When making contract termination decisions, NRCS may reduce the
amount of money owed by the participant by a proportion that reflects the good
faith effort of the participant to comply with the contract or the hardship
beyond participant’s control that have prevented compliance with the contract,
including natural disasters or events.
WHIP: The STC may allow a participant to retain any cost-share payments received
under the cost-share agreement in a proportion appropriate to the effort the
participant has made to comply with the cost-share agreement, or, in cases of
hardship, where forces beyond the participant’s control prevented compliance
with the cost-share agreement.
When the STC determines that any refund owed can be reduced, the reduction will
be based on all of the following: assurance that failure to perform the
remaining practices on the contract will not impair the effectiveness of those
performed; assurance that performed practices will provide conservation or
environmental benefits consistent with program objectives; and assurance that
performed practices will be operated and maintained by the producer for the life
span of these practices.
If cost recovery is required, the State Conservationist is responsible for
notifying the CPC participant. The State Conservationist will ensure that cost
recovery efforts are applied consistently and equitably among contract
participants. Interest will be calculated solely on the repayment of cost-share
funds previously paid to the participant. The interest payment does not apply to
liquidated damages or to any fund repayments waived by the State
Conservationist. Interest calculations will be prepared by the Programs
Management Staff at the State Office.
Compliance with program requirements and the amount of the cost recovery are
appealable items, as is either denial of waiver or partial waiver of the
recovery costs. Appeal rights and procedures will be followed according to
Appeals and Mediation policy in Part 510 of the 440-V-Conservation Programs
Manual, First Edition, Amendment 3, March 2001.
If the ASTC-FO determines cost recovery may be necessary they will forward the
necessary information found to the state program manager for the final decision
on cost recovery.
Because it would not be efficient or cost-effective, NRCS will not pursue
recovery costs and/or penalties for an amount less than $500.
< Back to Bulletins
|